Chartered Accountants ANZ
Chartered Accountants anz
Client: CAANZ
Location: Wellington
Type: Fitout
Value: $4.5M
Size: 1,500m²
Timeframe: 22 Weeks
BLACK delivered a sophisticated workplace fitout for Chartered Accountants Australia and New Zealand (CAANZ) at BNZ Place, transforming a base-build floor into a refined, high-performance environment. The project reflects a considered approach to materiality, spatial planning, and functionality, supporting both client engagement and staff wellbeing.
BLACK was engaged under an Early Contractor Involvement model to deliver a full office fitout across two levels, including demolition of the existing tenancy and delivery of new front-of-house and back-of-house environments.
The works included complete strip-out of the existing fitout, basebuild bathroom refurbishment, and make-good works to basebuild elements. New floor finishes were installed throughout, including solid timber, tile, carpet tile, and vinyl, alongside feature lighting and high-end joinery.
Front-of-house areas featured bespoke timber wall panelling and a refurbished lift lobby on Level 28, incorporating an antique mirrored ceiling. Back-of-house spaces included new meeting rooms and open plan work areas.
The project also included installation of new ceiling systems (2-way grid, perforated GIB, and solid), feature painting including Porters Paint finishes, operable walls with supporting structure, and mechanical and electrical basebuild modifications.
A key component of the project was a mid-project value engineering phase, requiring close collaboration with the client and consultants to align scope and budget while maintaining design intent. Delivery within a live tower environment required careful management of noise and vibration, particularly with tenants located below and adjacent to the works.
SOLUTIONS
Extensive fitout and Early Contractor Involvement (ECI) experience minimised RFIs and reduced variations during construction
Flexible and adaptive programme management enabled successful staged delivery and early handover
Demonstrated capability to balance programme acceleration with quality, safety, and cost control